Question 1 of 25
A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave. What should the project manager do next?
Show answer
How others answered
- A99%
Explanation
Hint is PM already identified this risk during Project Planning. Output of Identify Risk process is Risk register. Basically, a good PM w/ 4 values & 12 principles under PMI languages need to do this task with due diligent thus Risk register can be used later as sufficient reference regarding risk response plan when relevant risk happen. A is still the correct answer.
Adapted from community discussion by Hao2 · 2024-09-19 · 26 community upvotes. Third-party contribution; reviewed by our quality filter, not independently verified.