You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?
Show answer
How others answered
- A67%
- D33%
Only 67% agreed on this answer — treat it as contested rather than settled.
Explanation
Answer A : Analogous estimating is a technique that uses information from a similar past project in order to estimate the cost and duration of a planned project. This approach is often used when there is limited data available for a project, making it difficult to generate accurate estimates.