Once the make-or-buy analysis is completed, which document defines the project delivery method?
Show answer
How others answered
- B81%
- A19%
Explanation
B is correct. Once the make-or-buy analysis is completed, the document that defines the project delivery method is the "Procurement Strategy." The procurement strategy outlines how the project will obtain the necessary goods, services, or works. It includes decisions on whether to make in-house, buy from external sources, or use a combination of both approaches. The procurement strategy is a key component of the overall project management plan and helps guide the procurement activities throughout the project.