A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
Show answer
How others answered
- C40%
- A40%
- B20%
Only 40% agreed on this answer — treat it as contested rather than settled.
Explanation
Submit a change request. A. No contingency plan B. doesn't address problem D. does not follow the change control process E. Too early to escalate